Previous Page | Next Page Contents Glossary Index Appendix B. Work Sheets >

Physical Planning Work Sheet

The physical planner:

Use Table 44 as a work sheet when preparing the site for the printer.

Table 44. Infoprint 4000 and Infoprint 4100 physical planning work sheet
Weeks before Delivery Task Assigned to: Scheduled Completion Date:
15
  1. Identify the location for the printer and arrange for any necessary changes to the site.
  2. Identify a delivery route to the location of the printer.
  3. Prepare a layout plan.
  4. Determine the requirements for electrical outlets. If you are installing an Air Bearing Buffer/Flipper Unit or an Infoprint 4100 HS2 or HD3/4, you will need additional outlets. See Power Outlet and Cable Summary for more information.
  5. Order the 'H' configuration unique items, such as the turnbar/flipper and adapter piece (RPQ 8B4056).
 

___________

___________

___________

___________

___________

 

___________

___________

___________

___________

___________

10
  1. Install and test the electrical wiring and outlets.
  2. Verify that a forklift and operator will be available when the printer arrives.
 

___________

 

___________

 

___________

 

___________

Arrival
  1. Unpack the printer and inspect it for external damage.
  2. Move the printer to the prepared site.
 

___________

 

___________

 

___________

 

___________