Previous Page | Next Page Contents Glossary Index Preparing the Physical Environment >

Installation Requirements

A service representative installs the printer. However, you are responsible for the following pre-installation tasks:

Figure 43. Power distribution system

  1. Grounding terminal bar electrically attached (bonded) to enclosure and building steel
  2. Remotely operated power service disconnect
  3. Neutral bus
  4. Circuit breakers of appropriate size
  5. Branch circuits
  6. Customer-supplied receptacles/connectors in accordance with local codes
  7. Conduit electrically attached to enclosure
  8. Ground
  9. Service entrance ground or suitable building ground interconnected with all other grounds
  10. Neutral